NOTICE OF ACCEPTANCE AND

FINAL SETTLEMENT FOR MUNICIPAL

CONSTRUCTION

Pursuant to Wyo. Stat. §§ 16-6-

116, Notice is hereby given that

the City of Sundance, Wyoming,

has accepted as completed

according to plans, specifications,

and rules governing the same,

the work performed under that

certain contract dated 6 July 2021,

between the City of Sundance,

Wyoming, and Hot Iron, Inc. PO

Box 1067, Gillette, WY 82717 the

Contractor, for construction of the

City of Sundance’s Kid Tank and

Water Line Replacement Project

and the Contractor is entitled to

final payment therefore: that the

City of Sundance will cause said

Contractor to be paid the full

amount due to them under said

contract upon the 41st day after

the date of the first publication.

The date of the first publication

of this notice shall be the 29th

of September 2022. The date for

payment of the final settlement

shall then be the 9th of November

2022.

The City of Sundance, Wyoming.

BY: Paul Brooks, Mayor

Publish: September 29, October 6

and 13, 2022

 
 