City projects coming back online
April 14, 2022

Jeff Moberg
Work will soon resume on the Sundance Kid water tank replacement at the foot of Sundance Mountain soon.
After going dormant for the winter, the project to replace the Sundance Kid water tank will be coming back online in the next couple of weeks and hopefully complete by the summer. Meanwhile, the council has authorized its first infrastructure project of the year: an overhaul of the chlorination facility near the Cole tank.
Karla Greaser of city engineers Trihydro told the Sundance City Council last week that she is currently working with the contractor on a revised schedule for the Sundance Kid tank. Work will hopefully restart in mid-April, she said, and the hope is to create a condensed s...